Night-time barge towing, Copyright @MPA Singapore
Facing a severe congestion crisis due to global shipping disruptions, Singapore’s port operations were significantly impacted by the diversion of vessels around the Cape of Good Hope. At the end of May, the world’s second-largest container port saw berthing delays extend to up to seven days and a staggering backlog of 450,000 TEU awaiting dock space, according to Linerlytica. The congestion was further exacerbated as some carriers omitted planned Singapore port calls, shifting additional volumes to downstream ports.
In its latest update, the Maritime and Port Authority of Singapore (MPA) said that, together with PSA Singapore, it has managed to cut the average waiting time for container berths to under one day. The port added that enhanced operational efficiency has enabled most container vessels to complete their cargo handling and bunkering within a day of arrival.
Key measures contributing to this turnaround include the commissioning of new berths at Tuas Port, the reactivation of berths and yard spaces at Keppel Terminal, and increased manpower capacity. Additionally, the port has completed a four-month trial of night-time barge operations to and from Pasir Panjang Terminal (PPT). The trial included six barge operators and saw night movement of line-towed container barges to and from PPT between 7:00 pm and 6:30 am.
“This initiative was part of MPA’s ongoing efforts to review its rules and regulations to reduce business costs and turnaround time, enhance resource optimisation, while ensuring safety. Previously, night movement for line-towed container barges was only permitted at Brani and Keppel Terminals, where navigational traffic is less complex than around PPT,” MPA Singapore said.
“This initiative will fully utilise the night window to transport containers on barges into and out of the Port of Singapore and neighbouring ports, including those for transhipment. By enabling more containers to be delivered on barges throughout the day at PPT, this measure will improve connectivity with regional ports, enhance port efficiency, reduce the time container and feeder vessels spend at berth, and the need for containers to be transported between land terminals. Each line-towed barge can carry an average of 300 TEU.”
The port authority added that it would implement additional safety measures tested during the trial to ensure the safe movement of line-towed container barges at night. These include compulsory pilotage for the barges, restrictions on the length of towing lines, and close monitoring of barge movements by MPA’s vessel traffic management system. All night movements of line-towed container barges to and from PPT must receive prior approval from MPA. The port authority noted that barge operators have been briefed on the safety measures and approval process for night movements. The initiative takes effect from September 4.
The total number of containers handled by the Port of Singapore in the first seven months of 2024 amounted to 23.82 million TEU, marking a 6.1% increase in container volumes over the same period last year.
News report courtesy of by Jasmina Ovcina Mandra, World Cargo News.